Deck Fascia

Plan Type I - 18 lineal feet All items to be removed from the deck area by the homeowner/tenant prior to the commencement of work. At each location, perform the following:

  1. Place protection to the surrounding area.
  2. Remove the lags from the guardrail and shore in place.
  3. Sawcut and demo the deck coating for access to the edge metal flashing and dispose of.
  4. Demo the deck edge metal flashing and dispose of.
  5. Demo the 2x12 and 1x3 deck fascia and dispose of.
  6. Inspect the exposed area for damage - provide an addendum scope and cost if found.
  7. Pre-prime and pre-paint the new materials prior to installation.
  8. Install the new materials with galvanized fasteners.
  9. Install new 26 gauge bonderized edge metal flashing.
  10. Patch back the deck coating.
  11. Spot prime and spot paint the edge metal and fastener attachment points.
  12. Reattach the guardrail and remove the shoring.
  13. Remove the protection and clean up.
  14. Remove all debris from site.