- Remove all in planter light fixtures and save for the HOA.
- Shut off the irrigation.
- Cap off the irrigation.
- Removal all existing landscaping and irrigation and dispose of.
- Remove existing soil and dispose of.
- Scrape off the existing waterproofing and dispose of.
- Inspect the exposed surface for structural damage - report to HOA if found.
- Inspect the existing drains for damage - report to HOA if found.
- Apply Elasto-Poxy Primer VOC and allow to tack.
- Apply the 1st coat of Elasto-Deck B.T. waterproofing at 45 mils.
- Apply fiberglass mesh into the B.T and allow to cure over night.
- Apply the 2nd coat of Elasto-Deck B.T. waterproofing at 45 mils and allow to cure over night.
- Provide inspection from manufacturer to insure installation methods.
- Allow materials to cure.
- After the materials have cured perform a water test.
- Drain the planters.
- Install drainage mat.
- Install termination bar.
- Install PB4 protection board.
- Import 12" of rock base, filter fabric and new soil to previous height.
- Clean up.
- Remove all debris from site.